Czech Republic Delivery 2021
Residence Jubileum, Prague 7
A brownfield site in the centre of a city block in Holesovice with many neighbours. Permitting was difficult and delays suffered due to needing a review by the Main City
SIZE
- 105 Apartments
- 900m2 Offices
- 300m2 Retail
TIMING
- 2006 – 2011
SCOPE
- Development Management
Residence Meopta, Prague 5
Partly new build on a brownfield site, partly conversion of an existing factory in Cibulka, Kosire. Permits obtained for Planning and Building Permits before selling to YIT
SIZE
- 80 New Apartments
- 200 Apartments within a converted Factory
TIMING
- 2008 – 2014
SCOPE
- Development Management
Tesla Properties, Prague 9
Brownfield site in Hloubetin. Planning Permits sought for mainly residential with some offices.
SIZE
- 120,000 m2
TIMING
- 2009 – 2011
SCOPE
- Permitting
7 Stefanikova Street, Prague 5
Conversion of a roof space into 8 luxury apartments. Possibly one of the largest roof space conversions in this type of building totalling 1,000m2. Construction carried whilst the residents were living underneath.
SIZE
- 8 Apartments
TIMING
- 2015 – 2019
SCOPE
- Development Management
Keystone, Karlin, Prague 8
Due Diligence and Project monitoring services for a Munich based Investment Fund. (GLL Real Estate Partners)
SIZE
- 6,500m2
TIMING
- 2010 – 2012
SCOPE
- Due Diligence
Prozek, Prague 9
Design Management of a concept for an existing retail complex to be demolished and a new mixed use complex of apartments and retail.
SIZE
- 220 Apartments
- 4,500m2 Retail
TIMING
- 2018
SCOPE
- Design Management
Maly Brevnov, Prague 6
Work in progress on a new build of 23 Apartments In Prague 6. Currently in the Permitting phase with Construction due to start in April 2021.
SIZE
- 23 Apartments
TIMING
- 2018 – 2022
SCOPE
- Development Management
Cibulka haj, Prague 5
Currently in the permitting phase, This development is nestled in an established area near to a school and adjustment to a small forest.Construction due to start in November 2021
SIZE
- 10 Apartments
TIMING
- 2018 – 2022
SCOPE
- Development Management
Hloubetin Metro Plaza, Prague 9
Currently in the Concept and Public Participation phase. This development is adjacent to an established retail and office complex.
SIZE
- 58 Apartments
TIMING
- 2019 – 2023
SCOPE
- Development Management
Mejstrikova ulice, Haje, Prague 11
Another project currently in the Concept and Public Participation phase. This is the demolition of a redundant retail centre and the construction of a Residential complex with convenience retail.
SIZE
- 10 Apartments
TIMING
- 2018 – 2022
SCOPE
- Development Management
U Vetrniku, Brevnov, Prague 6
The rezoning of land currently classified for sports use. Using the last wave of rezoning applications before the new Metropolitan plan is in force.
SIZE
- 100 Apartments
TIMING
- 2019 – 2021
SCOPE
- Permitting Management
Czech Republic prior to 2003 at senior management level
ECM Radio Plaza, Prague
The building was begun as the state studio and radio centre in 1984, but construction was halted. The refurbishment will include office and administration areas. The new build works will include office space, a 15-screen multiplex cinema, retail area plus parking. At 27 stories, the development is currently the tallest in Prague.
CLIENT
- ECM Radio Plaza, a.s.
VALUE
- € 101 M / US $101.76 million / £70 million
TIMING
- Jan 1999 – Jan 2003
SCOPE
- Project Management
Riverside Brickworks, Prague
Re-construction of a former Brick factory into an office/retail center.
CLIENT
- COPA.
VALUE
- € 5.57 M / US $5.6 million / £3.8 million
TIMING
- Nov 2000 – Dec 2001
SCOPE
- Construction Management
Eurotel, Prague
The client required a new building with at least 20,000m², close to main thoroughfares, with the latest building technology. Preferring to lease, Bovis Lend Lease found a suitable site and separate developers (BBC for building A and PST Investment for building D) are supplying the building as per Eurotel’s specifications.
CLIENT
- Eurotel Praha spol, s.r.o.
VALUE
- Building A – € 27.4 M / US$27.6million / £19 million
- Building D – € 3.98 M / US$4million / £2.7 million
TIMING
- Completion March 2002
- Building A – 84 weeks
- Building D – 68 weeks
SCOPE
- Consultancy
Olympia Shopping Centre, Modrice
Phased construction of western-style shopping centre:
Phase 1 – 19,000m² hypermarket
Phase 2 – mall area with 14,000m² of individual shop units and a 5,500m² multiplex cinema for Ster Century
Phase 3 – second main store unit, occupied by Asko furniture.
CLIENT
- Tri Stannifer Project, a.s.
VALUE
- € 37.8 M / US $ 38 million / £26.33 million
TIMING
- Phase 1: Aug 1997 – Oct 1998
- Phase 2: January – December 1998
- Phase 3: February – November 2000
SCOPE
- Construction Management
Ahold Hypermarkets, Czech Republic and Slovakia
The success of the Olympia Centre (Modrice) led to a steady flow of new projects and further fit-outs for Ahold:
Modřice 10/1998 € 3.1 M / US $3.15 million
Ostrava 01/2000 € 3.1 M / US $3.15 million
Olympia Teplice 11/2000 € 3.28 M / US $3.33 million
Olympia Mlada Boleslav 11/2000 € 3.28 M / US $3.33 million
CLIENT
- Ahold
VALUE
- In excess of € 24.85 M / US$ 25 million / £17 m
TIMING
- Oct 1998 – Oct 2002
SCOPE
- Project Management
Ahold Warehouses, Klecany and Nemilany
Construction of the main distribution centre for Ahold. Phase 1 consists of 35,000m² of storage space including 100 loading bays.
Additional storage space (15,000m²) and modernisation of a second Ahold warehouse facility at Nemilany.
CLIENT
- Ahold Real Estate a.s.
VALUE
- € 15.6 M / US $ 15.7 million / £ 10.8 million (Klecany)
- € 3.18 M / US $ 3.2 million / £2.2 million (Nemilany)
TIMING
- 2000 – 2001
SCOPE
- Construction Management
Tesco Stores, Czech Republic and Slovakia
In 1996 Tesco entered the Czech Republic with the purchase of 14 K-mart stores. David Werry headed up the Due Diligence Team. The exercise was completed in 3 weeks.
CLIENT
- Tesco Stores
VALUE
TIMING
SCOPE
Slovansky Dum, Prague
Mixed-use retail, office, entertainment development. The project was to restore the area as a public meeting place over 5 phases, including refurbishing a baroque palace, a 19th century hotel and a 20th century casino and constructing three new buildings.
CLIENT
- PKSC, s.r.o.
VALUE
- € 33.4 M / US $33.6 million / £23.3 million
TIMING
- March 1999 – Feb 2001
SCOPE
- Construction Management
CentroZlin Shopping Centre, Zlin
New 40,000m² shopping centre. Tenants include Baumax, Carrefour and many individual shops in the mall area.
CLIENT
- Citygrove Europe
VALUE
- € 14.2 M / US $14.3 million / £9.7 million
TIMING
- May 1999 – Aug 2000
SCOPE
- Construction Management
Prague Congress Centre
The original 1,700 m² Congress Hall has been up-graded with more than 3140 extra seats and state-of-the-art acoustic, audio-visual and lighting equipment. The 1,000 m² stage can be raised or lowered hydraulically. The 1,077 m² Forum Hall, situated on the third floor, has also been modified.
CLIENT
- Kongresove Centrum Praha, a.s.
VALUE
- € 79.6 M / US $80 million / £54.5 million
TIMING
- Aug 1997 – June 2000
SCOPE
- Project Management
Domacnost Building, Lazarska 3, Prague 1
Refurbishment and fit-out of a 6-storey, historic building. The facade has been fully restored and 3,500 m2 of lettable office space has been created, for the Dutch tenant, ABN AMRO Bank.
CLIENT
- Pro Quality Ltd. – Canada
VALUE
- € 5.47 M / US $5.5 million / £3.8 million
TIMING
- March – October 1997
SCOPE
- Project Management
Airbag Production Facility, Jevicko
10,000 m² facility for the production of automotive safety airbags. The main building comprises a 7,500 m² single-storey production and storage area and a 2,500 m² two-storey office block. The production area houses CNC computer controlled sewing machines and over 100 manually-operated industrial sewing machines.
CLIENT
- Automotive Safety Components International s.r.o.
VALUE
- € 4.27 M / US $4.3 million / £3 million
TIMING
- June 1996 – Feb 1997
SCOPE
- Construction Management
Gallery of Modern Art, Prague
Reconstruction and restoration of the Veletrzni Palace, creating a spacious and striking new gallery with offices and a restaurant. It now provides 16,700 m² of exhibition space on four floors.
CLIENT
- National Gallery in Prague
VALUE
- € 6.9 M / US $7 million / £4.8 million
TIMING
- June 1995 – Jan 1996
SCOPE
- DMC
BP / Bovis Alliance
Alliance agreement for the upgrading and new build of the BP petrol stations across Europe (including Czech Republic), Japan and USA
CLIENT
- BP Amoco
VALUE
- circa € 485.7 M pa
- (US $488 million / £304.5 million)
TIMING
- extended to 2005
SCOPE
- Project Management
Project Delivery experience in other locations between 1989 and 2003 at senior management level
Marks & Spencer, Dortmund
Renovation of existing department store (14,400 sq ft)
CLIENT
- Marks & Spencer GmbH
VALUE
- DM 18.7 million / € 9.6 M / £6 million
TIMING
- March – October 1998
SCOPE
- Management Contractor
CentrO, Oberhausen
Regeneration program in the Ruhr valley, including 70,000 m² shopping centre, 11,500 seat multi purpose arena, 8 hectare leisure park, 9-screen cinema and promenade including restaurants, pubs and theatres.
CLIENT
- P&O / The Stadium Group (Joint Venture)
VALUE
- DM 1000 million / € 511.3 M / £320.6 million
TIMING
- Sep 1992 – Sep 1996
SCOPE
- Project Management
Merck Sharp Dohme HQ, Munich
Construction and fitting out of a four-storey 23,000 sq.m. building with computer centre, staff cafeteria and three internal courtyards.
CLIENT
- MSD
VALUE
- DM 70 million / € 35.8 M / £22.4 million
TIMING
- 1992 – 1994
SCOPE
- Construction Manager
Okhotny Ryad Retail Centre, Manezhnaya Square, Moscow
70,000m², 4-storey underground shopping centre.
CLIENT
- Moscow City Government
VALUE
- US$250 million / € 248.75M /
TIMING
- Completed August 1997
SCOPE
- Project Management
P&O Logistics, Budapest, Hungary
Construction of a 40,000 m² high bay (8m) warehouse and 2,000 m² office building, access roads and public utilities network.
CLIENT
- P&O Trans European Hungary
VALUE
- € 12.9 M / US $13 million /£8.78 million
TIMING
- 1995 – June 1997 (phase 1)
- 2000 (phase 2)
SCOPE
- Construction Management
La Manga Club Resort, Murcia
Development of a leading tourist resort, roughly the size of Monaco. To date we have constructed 36 individual, 80 2 and 3-storey town houses and 32 bungalows next to the golf course. Refurbished and extended the 5-star Principe Felipe Hotel and built the Hyatt Casino. Currently constructing 13 4-star apart-hotels.
CLIENT
- Inmogolf, S.A.
VALUE
- 37,500 million Ptas / € 225 M / £137.5 million
TIMING
- 1986 – 2003
- (various projects and phases)
SCOPE
- Management Contracting
The Arts Hotel, Barcelona
Construction of a 48-storey hotel complex, the highest in Spain at the time, consisting of a Ritz Carlton Hotel on 32 floors, offices and luxury apartment suites on 12 floors, a convention centre and conference facilities, health resort, shopping complex, dining facilities and a 536 space underground car park. The project also included a 6-storey office block next to the Tower.
CLIENT
- Travelstead Group
VALUE
- 23,000 million Ptas / € 138 M / £86.4 million
TIMING
- Aug 1990 – March 1994
SCOPE
- Construction Management
LEGOLAND Bavaria, Germany
LEGOLAND Deutschland opened its gates on 17 May 2002. Covering 120 acres and offering more than 40 attractions, it is considered ‘best of version’. LEGO Models throughout the park are animated and in some areas such as Miniland, can be controlled interactively by visitors, whose ages range from 3 to 13.
CLIENT
- LEGOLAND Deutschland
VALUE
- € 50 M / £31.25 million
TIMING
- August 2000 – May 2002
SCOPE
- Management Contracting
LEGOLAND, Windsor, UK
Unique family park for the pre-teens set in 140 acres of Windsor Great Park. The heart of LEGOLAND shows European cities and villages recreated in astonishing detail from millions of LEGO bricks. As well as rides, shows, attractions and playscapes, the park includes interactives, workshops, retail, food, and beverage outlets.
CLIENT
- LEGO A/S
VALUE
- € 136 M / £85 million
TIMING
- Jan 1994 – March 1996
SCOPE
- Construction Manager
Dar al Fouad Hospital, Cairo
Construction of the 100-bed hospital for cardiac, thoracic, vascular and nervous diseases, on a 10 acre (42,000 sq m) greenfield site, situated 32 km from the centre of Cairo. This facility is operated in co-operation with the Cleveland Clinic and Texas Heart Institute, USA.
CLIENT
- Egyptian Medical Consultancy Group
VALUE
- € 50 M / £31 million
TIMING
- 1996 – Sep 1998
SCOPE
- Project Management
Paternoster Square, St Pauls, London EC4
Development of 5 separate office buildings (next to St Pauls Cathedral) built around a spacious open loggia and Corinthian column. Christ Church Court, Juxon House, Warwick Court and St. Martins Court. King Edward Court (32,527 sq.m) will be home to the London Stock Exchange.
CLIENT
- Mitsubishi Estate Company
VALUE
- € 224 M / £140 million (total development)
TIMING
- August 1998 – ongoing
SCOPE
- Construction Manager
Scottish Equitable HQ- Edinburgh, Scotland
New 34,000 sq.m four-storey HQ on a 20 acre site, designed around a large central garden courtyard.
CLIENT
- Scottish Equitable Plc
VALUE
- € 86 M / £52 million
TIMING
- Dec 1993 – April 1996
SCOPE
- Construction Management
European Investment Bank (EIB), Luxembourg
Having successfully constructed the original building, BLL was named by EIB to undertake the 22,000 m² extension of its Headquarters.
CLIENT
- European Investment Bank
VALUE
- € 53.5M / £33.4 million
TIMING
- Sep 1991 – March 1995 (182 weeks)
SCOPE
- Project/Construction Management
Experience in UK 1973 – 1988
SAS Hotel, Buckingham Gate, London – Hotels
Pembroke Road, London – Residential
Anchor Brewery, Tower Bridge, London – Residential
Anchor Boiler House, Tower Bridge, London – Residential
Marks and Spencer, Gravesend – Retail
Marks and Spencer, Bexleyheath – Retail
Sainsbury SavaCentre Hypermarket, Basildon – Retail
Sainsbury SavaCentre Hypermarket, Gillingham – Retail
Sainsbury SavaCentre Hypermarket, Newcastle – Retail
Sainsbury Supermarket, Bedford – Retail
Buckingham Gate, London Offices
32 Bedford Square, London – Offices
Brompton Road, London – Offices
6 Stratton Street, London – Offices
28 Bedford Square, London – Offices
54 Russell Square, London – Offices
52/53 Russell Square, London- Offices
29 Bedford Square, London – Offices
56, Buckingham gate, London – Offices
Curzon Street, London – Offices
Barclays Bank, Kingston – Offices
Wembley Arena improvements, – London Exhibition